1. Get the drawing set in order.
Start with the drawing index, the specifications and every addendum issued so far. Check the sheets you received against the index and ask for anything missing before you measure.
Name or bookmark the sheets so you can find them again: plans, reflected ceiling plans, elevations, sections, details and schedules. Then note the sheets that carry your trade. A drywall estimator works from the architectural plans and wall types. An electrical estimator needs the power, lighting and one-line sheets. A concrete estimator starts with the foundation plan and the structural notes.
Read the general notes and your trade's specification before measuring. A note such as "all partitions extend to deck" or "provide two finish coats" changes quantities across the whole job.
2. Set the scale on every sheet. Then check it.
A PDF has no scale of its own. You tell the takeoff tool what a distance on the sheet represents, usually from the scale in the title block or under each view.
Do not trust that number alone. Sheets get printed to fit, reduced to half size or scanned slightly out of square. Details and enlarged plans often use a different scale from the main plan on the same sheet, and some views are marked not to scale.
Check every scale against a known dimension before you measure:
- Find a long written dimension on the view, such as a grid spacing or an overall building dimension.
- Measure it with the scale you set.
- If the measured length does not match the written dimension, calibrate from that dimension and measure it again.
- Repeat for each view on the sheet that uses a different scale.
- Plan drawn at 1/4" = 1'-0" on a 24 × 36 sheet, printed at half size on 12 × 18
- Effective scale on the print: 1/8" = 1'-0"
- A 30'-0" grid measured at the title-block scale reads 15'-0"
Use a long dimension for the check. A small clicking error matters less over 30 feet than over 3 feet.
Where a written dimension and a scaled length disagree, use the written dimension and record the conflict as a question if it changes your quantity.
3. Pick the right kind of measurement.
Most quantities come from a few kinds of takeoff. Choose the one that matches how the item is bought and installed.
| Kind | Unit | Examples |
|---|---|---|
| Area | SF, SY, squares | Slabs, flooring, ceilings, roofing, wall finishes |
| Linear | LF | Partitions, footings, curb, base, conduit, piping, fencing |
| Count | EA | Doors, receptacles, light fixtures, plumbing fixtures, spread footings |
| Assembly | Any | One measurement that carries several parts, such as a wall type or a fixture with its box and whip |
Many wall and surface quantities start as a length. Measure the wall's length, apply its height and you have the area of one face:
- 240 LF of wall × 9.0 ft high = 2,160 SF per face
- Board on both faces: 2,160 × 2 = 4,320 SF
Sloped surfaces need the slope applied. A roof measured in plan is smaller than the roof itself:
- Slope factor = √(1 + (6 ÷ 12)²) = √1.25 ≈ 1.118
- 2,400 SF in plan × 1.118 ≈ 2,683 SF of roof
- 2,683 ÷ 100 SF per square ≈ 26.8 squares
Cut openings that are not part of the work out of the area as you measure it, such as a stair opening in a slab or a skylight in a roof. It is harder to remember a deduction later.
4. Set up groups before you measure.
Decide how the takeoff will be split before the first measurement. Match the split to the way the price has to be reported: by floor, building, area, phase or alternate.
A bid form that asks for a separate price for Building B, or an alternate for the second-floor fit-out, is easy to answer when those quantities were kept apart from the start. Moving measurements between groups afterwards is slow and easy to get wrong.
Keep alternates in their own groups. Keep demolition, existing work and new work apart where the scope differs.
5. Measure typical floors once.
When several floors are the same, take off one typical floor and repeat it for the others. Confirm they really match first. Check the plan for each floor, not only the note that says typical.
- Floors 3 through 7 are typical: 7 - 3 + 1 = 5 floors
- Typical floor: 186 duplex receptacles
- Total: 186 × 5 = 930 receptacles
Count the floors carefully. Floors 3 through 7 is five floors, not four. Take off anything that differs on a single floor, such as a larger tenant space or an added stair, as its own item outside the repeated quantity.
6. Let one measurement carry its parts.
Most items are made of more than one material. A metal stud partition needs studs, top and bottom track, board, screws, tape and compound. A receptacle needs a box, a ring, a device, a cover plate and its share of conduit and wire.
Build these as assemblies: one takeoff item whose parts each have a formula on the measured quantity. Measure 400 LF of a wall type, and the parts give the studs from the spacing, the track from the length and the sheets of board from the wall area.
Write the formulas once, check them on a small example you can work by hand, and reuse them. The drywall takeoff guide and the electrical takeoff guide show worked examples.
7. Work in an order you can check.
- Take off one sheet at a time, in the same order on every job.
- Use a different color for each item, so the sheet shows what has been measured.
- Reconcile counts with schedules: doors on the plans against the door schedule, fixtures against the fixture schedule, footings against the footing schedule.
- Check the reflected ceiling plans, elevations and details for work the floor plans do not show.
- Keep a list of questions as you go. Unresolved ones become clarifications in the proposal.
A finished sheet should show every measurement on the drawing. Anyone reviewing the takeoff can then see what was counted and what was left out.
8. Update the takeoff when drawings change.
Addenda and revised sheets arrive during most bid periods. Compare each revised sheet with the one it replaces, find the changed areas and update the measurements on those areas.
Read the written addendum items as well. A narrative change, such as a new paint type or a changed wall rating, may come without a revised drawing.
Keep the superseded sheet with the job. If the GC asks why a number changed, you can show both versions.
9. Carry the quantities into the price.
A takeoff quantity is a net quantity. Before pricing, turn it into what you buy and install:
- Add waste or loss at your company's rate for each material.
- Round up to purchase units: sheets of board, sticks of conduit, gallons of paint, cubic yards of concrete.
- Apply labor from your production rates or from crew size and time.
- Add equipment such as lifts, pumps and scaffolding where the work needs it.
Keep the link from each priced line back to its takeoff item and sheet. When a quantity changes, you can update the price from it and explain any line on the estimate.
Checklist before you price.
- Drawing index checked against the sheets received.
- All addenda logged and applied.
- Scale set and checked against a known dimension on every view you measured.
- Groups match the bid form, alternates included.
- Typical floors confirmed and multiplied correctly.
- Schedules reconciled with plan counts.
- Openings and cut-outs handled the same way throughout.
- Open questions listed for the proposal.
The same takeoff in Kredna.
In Kredna you add the PDF set, then set each sheet's scale by calibrating against a known dimension or picking a standard scale, and check it against a printed dimension. A region gives part of a sheet its own scale. Press Space to pick an item, then measure counts, lengths and areas (with cutouts) on the drawing; the quantities total in the job tree as you go, in folders by area, level or system, and a folder can be marked as an alternate. When an addendum replaces a sheet, the old sheet is kept and its takeoffs are flagged for you to check.
See takeoff, and the trade pages for drywall, electrical, painting and structural steel.