Takeoff guide · 6 min read · updated November 10, 2026

How to do a drywall takeoff

A drywall takeoff measures each partition type by length, turns the length into board area with the wall height and the number of layers, and works out the board, studs, track and finishing materials from those quantities.

Get the wall types right first. Most drywall quantities follow from them.

1. Start with the partition types.

The partition type legend or wall type schedule is the key to the job. For each type, record:

  • Stud size, gauge and spacing, such as 3-5/8 inch studs at 16 inches on center.
  • Board layers on each side and the board type: regular, Type X, moisture resistant or abuse resistant.
  • Height: to the underside of the deck above, or to a set distance above the ceiling.
  • Insulation or sound attenuation blankets.
  • Fire or sound rating and the tested design it follows.
  • Finish level and any special finish.

Then find each type tag on the floor plans. A wall with no tag, or a tag that is not in the legend, is a question to raise before you price it.

Read the general notes too. A note such as "extend partitions 6 inches above the ceiling unless noted" sets the height of every wall it covers.

2. Measure length by type. Set the height.

Take off each wall type as its own item, floor by floor. Measure through door openings and deal with the openings in a separate step.

Set the height from the sections and the notes, not from one typical number. A wall to a deck 14 feet up is a different item from a wall to 6 inches above a 9-foot ceiling, even with the same stud and board.

Watch for walls that change height: under a sloped roof, along a stair, or stepping down at a soffit.

3. Turn length into board area.

Board area = length × height × number of board layers, counting every layer on both sides of the wall.

Type A partition
  • 3-5/8" studs at 16" o.c., one layer of 5/8" Type X each side, 10'-0" high
  • Length on the floor: 400 LF
  • Wall area per face: 400 × 10 = 4,000 SF
  • Board, one layer each side: 4,000 × 2 = 8,000 SF

A wall with two layers each side has four layers in total. A shaft wall or a furring wall may have board on one side only. Read each type rather than assuming two faces.

4. Decide how to handle openings.

Doors, windows and other openings remove board, but cutting around them still takes material and time. Many estimators deduct only large openings, such as storefronts or wide cased openings, and leave doors in. Pick a rule, write it down and apply it the same way on every job.

If you deduct, work out the area per opening and multiply by the faces:

Door deduction
  • 12 doors at 3'-0" × 7'-0" = 21 SF each
  • 12 × 21 = 252 SF per face
  • Both faces: 252 × 2 = 504 SF

Openings also add material: extra studs at the jambs, a header, and framing above the door.

5. Convert area to sheets with waste.

Board is bought by the sheet. Common 4-foot-wide sheets cover:

SheetArea
4 × 8 ft32 SF
4 × 10 ft40 SF
4 × 12 ft48 SF

Choose the sheet length that suits the wall height and the way your crews hang board, then add waste at your company's rate. Using 10% as an example rate:

Type A board
  • Net board: 8,000 - 504 = 7,496 SF
  • With 10% waste: 7,496 × 1.10 = 8,245.6 SF
  • 4 × 10 sheets: 8,245.6 ÷ 40 = 206.1, so 207 sheets

Keep each board type separate. Type X, moisture-resistant and abuse-resistant board are different items with different prices.

6. Work out studs and track.

Studs = length × 12 ÷ spacing in inches, plus 1 per wall run, then extra studs at corners, intersections and opening jambs.

Type A studs
  • 400 LF at 16" o.c.: 400 × 12 ÷ 16 = 300 spaces
  • One more stud per run, 20 runs: 300 + 20 = 320 studs
  • Example jamb rule, 2 studs per door, 12 doors: 320 + 24 = 344 studs

Add your own rule for corners and intersections. Order studs at the stock length that covers the height.

Check tall walls against the wall type. A wall to the deck may need a heavier gauge or closer spacing than the same type at ceiling height; the drawings or the stud manufacturer's limiting height tables decide it.

Track = length × 2, one run at the bottom and one at the top:

Type A track
  • 400 × 2 = 800 LF
  • In 10-foot pieces: 800 ÷ 10 = 80 pieces before waste

Walls that run to the deck often need a deflection track or slotted head at the top. Price it as its own item rather than as standard track.

7. Take screws, tape and compound from the board area.

Fasteners and finishing materials follow the board area. Set them up as factors per 1,000 SF of board, from your own records or the manufacturer's published coverage:

  • Screws per 1,000 SF, which depend on the framing spacing and on walls or ceilings.
  • Joint tape per 1,000 SF.
  • Joint compound per 1,000 SF, which depends on the finish level.
  • Corner bead and trim by LF of outside corners and edges, measured on their own.

Material = board SF ÷ 1,000 × your factor. The Type A walls carry 8,000 SF of board, so each factor is multiplied by 8.

The specified finish level, from Level 0 to Level 5, changes the compound and the labor. Level 5 adds a skim coat over the whole surface, so price it as its own finishing item.

8. Take off ceilings and soffits.

Measure drywall ceilings as areas from the reflected ceiling plan, with their framing: suspended drywall grid, furring channel on hangers, or framing to the structure.

Soffits and bulkheads need their bottom and their vertical face:

Soffit
  • 60 LF of soffit, 2'-0" wide, 1'-6" drop
  • Bottom: 60 × 2.0 = 120 SF
  • Face: 60 × 1.5 = 90 SF
  • Board: 120 + 90 = 210 SF, plus 60 LF of corner bead at the outside corner

Ceiling board is often hung at heights that need lifts or scaffolding. Note the ceiling height with the item so labor and equipment can be priced.

9. Treat rated walls as their own items.

Fire-rated partitions follow the tested design listed on the wall type. The design fixes the board type, the number of layers, the stud and the fastener spacing. Rated walls usually run to the deck above, and the head-of-wall joint and the penetrations through the wall need firestopping.

Confirm who carries the firestopping. On some jobs it is in the drywall scope. On others it belongs to a firestopping subcontractor or to each trade that makes a penetration. State it in the proposal either way.

Sound-rated walls may also call for acoustical sealant at the top and bottom, insulation and resilient channel. Read the type and the notes.

10. Check for what drywall takeoffs often miss.

  • Second layers, and one-sided walls taken off as two-sided.
  • Furring at columns, exterior walls and chases.
  • Shaft walls at elevators, stairs and duct shafts.
  • Backing and blocking for casework, grab bars, handrails and wall-hung equipment.
  • Control joints, corner bead, trim and reveals.
  • Access panels, where the drywall contractor installs them.
  • Insulation and sound blankets inside the walls.
  • Deflection track and head-of-wall details at the deck.
  • Tall walls that need heavier studs, lifts or scaffolding.
  • Patching and repair in renovation work.

The same drywall takeoff in Kredna.

In Kredna you measure each wall type as a linear takeoff with its height, so the wall area comes from length × height. The drywall and metal framing starter pack is included: its wall types are items whose parts are formulas on the takeoff, such as board from the wall area, studs from length and spacing, track from length, and the framing, hanging and taping labor. Change them to your own types once, and they are ready for every drywall bid after. The pack sets no prices: your company enters its own costs, and any part left unpriced is on the Not priced list.

See the drywall estimating page and the library.

Related

Worked examples use stated assumptions to show the arithmetic. Use your own waste rates, factors and stud rules, and the drawings' requirements, on a real bid.

Get the next bid moving.

See how Kredna handles the takeoff, the pricing and the scope behind your next bid.