Proposals guide · 6 min read · updated November 10, 2026

How to write a subcontractor bid proposal

A subcontractor bid proposal tells the GC what your price buys. It lists the documents you priced, the work included, the work excluded, the assumptions behind the number, and any alternates and unit prices the bid asks for.

A GC compares several bids for the same trade side by side. A clear scope makes your number easier to compare and easier to carry.

1. State the basis of the price.

Open with the project name, the GC, the proposal date and a revision number. List the drawings and specifications you priced, by sheet list or issue date, and acknowledge every addendum by number and date.

This proposal is based on the drawings and specifications dated [date] and Addenda 1 through 3, dated [dates].

If an addendum arrives after you price, issue a revised proposal with a new revision number rather than relying on a phone call.

State the base bid amount once, clearly. Keep alternates and unit prices apart from it.

2. Write inclusions the GC can check.

Describe the work in the terms of the drawings. Name the systems, areas and items you are carrying, and say whether you furnish, install or both. Examples from different trades:

Furnish and install metal stud partitions, types A through F, with gypsum board taped and finished to Level 4, as shown on the floor plans and wall types listed above.
Furnish and install the light fixtures in the fixture schedule, with branch circuits, devices, and connections to the mechanical equipment shown on the electrical drawings.
Prime and paint walls, ceilings, and hollow metal doors and frames as scheduled in the room finish schedule, one primer coat and two finish coats.

Match each inclusion to a line in your estimate. If the proposal names work the estimate does not carry, fix one or the other before it goes out.

3. Make exclusions specific.

Exclusions say what related work you are not carrying. Make each one specific to the job and to your trade. A long standard list copied from another project can contradict the bid form or the specification.

  • Drywall: "Firestopping at the head of rated walls and at penetrations, by others."
  • Electrical: "Fire alarm devices and wiring; data and telecom cabling."
  • Painting: "Painting of exposed ductwork and piping above ceilings."
  • Concrete: "Excavation, backfill and subgrade preparation."

Check that each exclusion does not conflict with an inclusion or with a requirement of the bid documents. If the bid form puts work in your trade, an exclusion alone may not settle it. Ask the question during the bid.

4. Write clarifications and assumptions.

Clarifications explain how you read the documents where they are unclear, and the conditions the price depends on. Keep the ones that change how the GC reads your number.

Partitions are priced to 6 inches above the ceiling, except where the wall types show full height to the deck.
Slab pricing assumes ready-mix trucks can reach each pour. Pumping is included only where noted.

Turn your open questions from the takeoff into clarifications. If an RFI was answered, cite the answer.

5. Price alternates on their own.

An alternate should make sense read alone. Say what changes, whether it adds to or deducts from the base bid, the amount, and any other alternate it depends on.

Alternate 2, add: epoxy paint system at the kitchen and restroom walls in place of the base-bid finish. Add $[amount].

Use the alternate numbers and descriptions from the bid form, so the GC can line your prices up with the other bids.

6. Give unit prices in the units asked for.

Unit prices let the GC add or deduct work after award. Give them in the unit the bid form asks for, and say what each one includes.

  • Drywall: per LF of added type A partition, 10 feet high, both sides finished.
  • Electrical: per added duplex receptacle, with box, device, plate and branch circuit up to a stated length.
  • Concrete: per CY of added footing concrete, placed.
  • Painting: per door and frame, primed and two finish coats.

A unit price that leaves out the box or the conduit is hard to use later. State what is in it.

7. State schedule and access assumptions.

Labor is priced on assumptions about when and how the work happens. State the ones that matter to your number:

  • Number of mobilizations or phases priced.
  • Normal working hours, or overtime and off-hours where required.
  • Work areas available and ready when you start.
  • Hoisting, lifts and storage provided by you or by the GC.
  • Lead times for long-lead material, such as switchgear or special board.

If the bid documents require phasing, price the phases. Do not assume one continuous visit when the schedule says otherwise.

8. Name the work by others.

Some work touches your trade but belongs to someone else: sleeves set by the plumbing contractor, embeds supplied by the steel contractor, control wiring by the controls contractor. Name the trade or party, and say who supplies and who installs.

Anchor bolts furnished by the steel contractor and set by us.

The split often depends on the bid package. Read the GC's scope sheet for your trade and follow it.

When you install material that another party supplies, say who receives it on site, who stores and protects it, and who replaces it if it arrives damaged or short.

9. Answer the bid form as written.

Many GCs send a bid form or a scope sheet for each trade. Fill in every line it asks for, in its order and its units, even where your proposal letter explains the scope in more detail. A price the GC has to reorganize to compare is harder to carry.

Where the bid documents set an allowance, such as a sum for unforeseen patching or for a fixture not yet selected, show that it is included as written and how it will be adjusted against the actual cost.

Send the proposal before the bid deadline, to the address and in the format the invitation asks for. Keep a copy of exactly what was sent, with its revision number, so any later question can be answered from the submitted version.

10. Keep commercial terms consistent.

State how long the price is valid, any material escalation terms your company uses, and whether tax, bonds and permits are included. Keep these in line with your company's reviewed terms.

A proposal letter does not replace reviewing the subcontract. Carry the agreed qualifications into it.

Proposal checklist.

  • Project, GC, date and revision number shown.
  • Drawings, specifications and every addendum acknowledged.
  • Base bid stated once, clearly.
  • Inclusions match the estimate line by line.
  • Exclusions specific to this job and not in conflict with the inclusions.
  • Clarifications cover the open questions from the takeoff.
  • Alternates and unit prices use the bid form's numbers and units.
  • Schedule and access assumptions stated.
  • Work by others named, with who supplies and who installs.
  • Validity and commercial terms consistent with company terms.

The same proposal in Kredna.

In Kredna the proposal is generated from the job: the base bid from the recap, scope lines from the folders, and the job's inclusions, exclusions, clarifications, alternates and unit prices. The wording is yours to edit; the amounts are read from Pricing and can't be changed in the document. Exclusions and clarifications start from your company clause list, with job-specific entries added. You export the proposal to PDF or Word.

See scope and proposals, and the trade pages for drywall, electrical, painting and structural steel.

Related

These are scope-writing examples, not legal advice or contract terms. Keep your company's reviewed commercial terms and get appropriate review for contract-specific changes.

Get the next bid moving.

See how Kredna handles the takeoff, the pricing and the scope behind your next bid.