Takeoff guide · 6 min read · updated November 10, 2026

How to do a concrete takeoff

A concrete takeoff measures the footings, walls, slabs and other elements on the drawings, converts each one to cubic yards of concrete, and takes off the reinforcing, forms, vapor barrier and finishing that go with them.

Every volume comes back to one conversion: cubic feet ÷ 27 = cubic yards.

1. Read the foundation plan, schedules and notes.

Start with the structural general notes: concrete strengths, reinforcing grade, lap and cover requirements, and the typical slab and footing details. Then read the foundation plan with its footing schedule, the slab plan and the wall sections.

Check the architectural and civil sheets too. Slab depressions, ramps, stoops, curbs, equipment pads and site walks may appear only there.

2. Footings and piers.

CY = length × width × depth, all in feet, ÷ 27. Measure continuous footings by length and spread footings by count from the footing schedule.

Continuous footing
  • 220 LF, 2'-0" wide × 1'-0" deep
  • 220 × 2.0 × 1.0 = 440 CF
  • 440 ÷ 27 = 16.3 CY
Spread footings, type F1
  • 12 footings, 6'-0" × 6'-0" × 1'-6"
  • 6 × 6 × 1.5 = 54 CF each
  • 12 × 54 = 648 CF ÷ 27 = 24.0 CY

For round piers, CF = 3.1416 × radius² × depth. A 24-inch pier 10 feet deep is 3.1416 × 1² × 10 = 31.4 CF, or 1.16 CY.

3. Foundation walls.

Measure walls by length along the centerline, so the corners are not counted twice. Take the height and thickness from the wall sections and convert the thickness from inches to feet.

Foundation wall
  • 220 LF, 4'-0" high, 8" thick
  • 220 × 4.0 × (8 ÷ 12) = 586.7 CF
  • 586.7 ÷ 27 = 21.7 CY

Deduct large openings where the drawings show them. Take pilasters and thickened sections as their own items.

4. Slabs on grade and on deck.

CY = area in SF × thickness in inches ÷ 12 ÷ 27.

4-inch slab on grade
  • 10,000 SF × 4 ÷ 12 = 3,333.3 CF
  • 3,333.3 ÷ 27 = 123.5 CY

A quick check: at 4 inches thick, one cubic yard covers 81 SF (27 × 12 ÷ 4). At 6 inches it covers 54 SF.

Add the concrete a plain area leaves out: thickened edges, thickened slabs under walls, turned-down edges and depressions that change the thickness. Take each as a linear or area item with its own section.

Thickened edge
  • 400 LF of edge, 12" wide, 8" below the slab
  • 400 × 1.0 × (8 ÷ 12) = 266.7 CF ÷ 27 = 9.9 CY

For slabs on metal deck, follow the deck profile in the details. The volume is not the area times the total depth, because the deck flutes change the average thickness.

5. Add waste and round up to the order.

Ready-mix is ordered by the cubic yard. Add an allowance for uneven subgrade, over-excavated footings, spillage and the concrete left in the pump and the truck. Use your company's figures. They differ for footings poured against earth and slabs placed on a graded base.

Then round each pour up to the supplier's ordering increment. Small loads may carry an extra charge, so check the supplier's quote.

6. Rebar by spacing and laps.

Bars in one direction = length to cover ÷ spacing + 1. Each run of bar is its length plus its laps.

For a 100 ft × 100 ft slab with #4 bars at 12 inches on center each way, using 20-foot bars and an example lap of 2 feet:

Slab rebar
  • Runs per direction: 100 ÷ 1.0 + 1 = 101
  • Each run: 6 bars and 5 laps, 100 + 5 × 2 = 110 LF
  • One direction: 101 × 110 = 11,110 LF. Both: 22,220 LF
  • #4 at 0.668 lb/ft: 22,220 × 0.668 ≈ 14,843 lb, about 7.4 tons

This ignores edge cover, which shortens each bar slightly. Take lap lengths from the drawings or the lap schedule; they depend on bar size, concrete strength and location.

Bar sizeDiameterWeight
#33/8 in0.376 lb/ft
#41/2 in0.668 lb/ft
#55/8 in1.043 lb/ft
#63/4 in1.502 lb/ft

Footing and wall bars work the same way: longitudinal bars from the length and laps, transverse bars from the spacing. Count corner bars, dowels and hooks as their own items. Chairs, bolsters and tie wire follow the bar.

7. Welded wire mesh.

Welded wire reinforcement is taken off by area and bought in sheets or rolls. Add the side and end laps the drawings or the specification require, and the waste from cutting at edges and openings.

Mesh to buy = slab area × (1 + lap and waste allowance) ÷ area of one sheet or roll, rounded up.

8. Forms and edges.

Forms are measured in square feet of contact area (SFCA): the area of concrete face the form touches.

Wall forms
  • 220 LF wall, 4'-0" high, formed both sides
  • 220 × 4.0 × 2 = 1,760 SFCA

Footings poured against earth may need no forms. Where they are formed, take both sides: 220 LF × 1.0 ft deep × 2 = 440 SFCA.

Slab edge forms are measured by length. A 100 ft × 100 ft slab placed in one pour has 400 LF of edge. Construction joints between pours, bulkheads and blockouts add more.

9. Base, vapor barrier and insulation.

Under a slab on grade, take off the granular base, the vapor barrier and any insulation by area. Convert the base to cubic yards the same way as the slab: 10,000 SF of 4-inch base is also 123.5 CY compacted in place. If the supplier sells it by the ton, convert with the weight per yard from their quote and allow for compaction.

Vapor barrier is bought in rolls. Add the laps the specification requires and the turn-ups at walls and footings.

10. Finishing, joints and curing.

Price finishing by area for each finish: steel trowel, broom, exposed aggregate, hardener or sealer. Curing, protection, and hot-weather or cold-weather measures go with the slabs they apply to.

Take saw-cut control joints by length from the joint layout:

Control joints
  • 100 ft × 100 ft slab, joints at 12'-6" each way
  • 100 ÷ 12.5 = 8 bays, so 7 joint lines each way
  • 7 × 100 × 2 = 1,400 LF

Add joint filler or sealant if the specification calls for it.

11. Embeds, sleeves and work by others.

Many items are cast into the concrete but supplied by other trades. Decide what you furnish, what you install and what someone else sets before the pour:

  • Anchor bolts and embed plates, often furnished by the steel contractor and set by concrete.
  • Sleeves and blockouts for plumbing, electrical and mechanical, usually by those trades.
  • Waterstops, dowels and expansion joint material.
  • Elevator pits, sumps, trenches and equipment pads.
  • Pumping, testing and inspection.
  • Excavation, backfill and subgrade preparation.

Write the split into the proposal. If anchor bolts are furnished by others and set by you, say so.

Concrete takeoff checklist.

  • Structural notes read for strength, reinforcing, laps and cover.
  • Footings, piers and walls measured from the schedules and sections.
  • Slab thicknesses, thickened edges and depressions taken separately.
  • Volumes converted to CY and checked with a quick rule.
  • Waste added and pours rounded to the order.
  • Rebar counted by spacing, with laps, dowels and accessories.
  • Forms in SFCA and slab edges in LF.
  • Base, vapor barrier and insulation by area.
  • Finishing, joints and curing priced.
  • Embeds and by-others items written into the proposal.

The same concrete takeoff in Kredna.

In Kredna you measure slabs as areas, footings and walls as linear takeoffs and spread footings by count. Build your concrete items once in the library, with properties for the sizes and parts whose formulas work out the CY, forms and bars from the takeoff, and price them with your own costs. There is no concrete starter pack, so these items are yours to build.

See the concrete estimating page and the library.

Related

Worked examples use stated dimensions and an example lap length to show the arithmetic. Take laps, cover, waste and ordering increments from the drawings, the specification and your supplier.

Get the next bid moving.

See how Kredna handles the takeoff, the pricing and the scope behind your next bid.