Price basis: cost each, tag or lump sum

Price a material, equipment or subcontract part by a cost each, by a company tag, or as a lump sum. Set packs, whole packs, tax, and no-charge states.

Every non-labor part has one price basis. In the item editor's parts grid, the Price cell has three choices:

  • $ (cost each): a price per unit of the part, or per pack.
  • TAG: the value of a company tag, such as "Board 5/8" at $0.62/SF. See Tags.
  • LUMP: one amount, whatever the quantity.

A part with no price reads Missing and is never counted as $0.

Labor parts are priced by their basis and crew instead. See Labor parts.

Packs

Open the part's Advanced line (▸ at the start of the row):

  1. Type the Pack size, for example 1000 EA per BOX, and name the pack.
  2. Tick Buy whole packs to round up to whole packs.
  3. With a cost each, choose Price per the unit or the pack.

Whole packs are rounded for the item as a whole, after waste, not per takeoff. The line shows the result, for example "1,840 EA → 2 BOX".

Tax

Tick Tax on a part to make it taxable. The job's tax applies to taxable material by default. See Tax, bond and insurance.

Zero by choice

When a part really costs you nothing, say why. In the State cell, choose:

  • No charge
  • By others
  • Owner-furnished

The part counts as $0 on purpose and prints that way. Choose Priced to take the mark off.

Price in Pricing too

You can type a cost each, pick a tag or set a lump sum right in the Pricing grid. See Price parts in the grid.

Something here doesn't match what you see in the app? Tell us at support@kredna.com.